Add Predecessor to Tasks

One of the most powerful ways to make tasks dependent on each other is using predecessors. This is called adding dependency to a task. Let’s assume one of your tasks can’t start until another task in your project is completed. For example to install the windows, the wall needs to be finished. This could be accomplished by using predecessor. You have two tasks in your project. One called ‘build wall’, the second ‘install windows’. Go to task “Install widows” and type “build wall” in the box labeled ‘Predecessor’. After you press return, the application adjusts the start of the task ‘install windows’ to the next day after the task ‘build wall’ due date.